  • **Update** Pavement Preservation Work

    Jun 07, 2019 | Read More News
    Share this page

    Road Work AheadPima County Department of Transportation along with their contractor, Markham Contracting, will be milling and repaving at the following locations:

    Monday, June 10 through Tuesday, June 25: The contractor will be milling and repaving Magee Road from 1st Avenue to the end of the road. Work will consist of milling, repaving, and striping. Hours of operation will be from 6 a.m. to 6 p.m.

    Thursday, June 13 through Tuesday, June 25: The contractor will be completing the milling and repaving on Pontatoc Road from River Road to Sunrise Drive. Work will consist of milling, repaving, and striping. Hours of operation will be from 6 a.m. to 6 p.m.

    Thursday, June 13 through Tuesday, June 25: The contractor will be completing the milling and repaving on Hacienda del Sol from River Road to Sunrise Drive. Work will consist of milling, repaving, and striping. Hours of operation will be from 6 a.m. to 6 p.m.

    Motorists can expect lane restrictions and reduced speed. Sheriff’s deputies will be assisting through the work zone. Please approach the area with caution and obey all traffic control devices. Minor delays may occur during this work.

    In the event of mechanical failure or inclement weather, the construction schedule is subject to change.