  • Coronado Cougars Walkway and Bikepath at Wilds Road and Bowman Road

    Project MapProject Cost: $400,000
    Project Status: Completed
    Start Date:  July 13, 2015
    Completion Date: Fall 2015
    Engineer/Contractor: Falcone Brothers

    The Pima County Department of Transportation is facilitating this community-initiated project, funded by federal money, provided through the Arizona Department of Transportation.

    The project includes an asphalt multi-use path on the north side of Wilds Road from the east entry of Coronado School to Bowman Road, and on the west side of Bowman Road from Wilds Road to Golder Ranch Drive. Other features include: Handrail, concrete landings, concrete headers, cut-off walls and connector sidewalks.

    Community Relations

    Carol Brichta
    Program Coordinator
    Department of Transportation
    (520) 724-6410
    email Carol Brichta 

    Transportation Engineering

    Rick Ellis
    Acting As Project Manager
    Department of Transportation
    (520) 740-6410
    email Rick Ellis

    Coronado Path grading

    Coronado Path grading
    Coronado Path grading 2Coronado Path grading 3
    Follow UsShare this page

    Transportation

    Ana M. Olivares, P.E.
    Director

    201 N. Stone Ave., 4th Fl.
    Tucson, AZ 85701

    (520) 724-6410


    Department Home Page
    Department News
    Department Directory
    Feedback
    Boards, Commissions and Committees
    Report a problem
    Permitting
    Maps
    Volunteer