Tucson Electric Power Company (TEP) operates its Irvington Generating Station (IGS) under Class I Air Quality Operating Permit No. 1052 issued by the Pima County Department of Environmental Quality (PDEQ). IGS consists mainly of two steam boiler generating units, specifically, Unit 1, Unit 2 and ten reciprocating internal combustion engines.
December 13, 2018 - Facility Change
Decommissioning of Steam Generating Units Stationary Combustion Turbines Units 1 and 2 Facility Change Notification Dispersion Modeling Report - Rev 3 Pluvue II - Rev 1
Correction of Federal Register
Federal Register Notice PSD Permit Effective Letter
EAB December 3, 2018 (Order Denying Review)
EAB Dockets 2018-03-29 Sierra Club TEP RICE Comments Exhibit 1 Petra Pless CV Exhibit 2 KDEH Lacey Randall Final Permit Exhibit 3 Tradewind Lacey Randall Application Exhibit 4 CARB BACT Determination for Neo California Exhibit 5 SCAQMD BACT Neo California Exhibit 6 GAO Report Exhibit 7 EPA Letter to Broadbent, BAAQMD Exhibit 8 EPA Letter to Rhodes, FDEP Exhibit 9 Jahnke Exhibit 10 NCUAQMD Permit for Humboldt Bay Exhibit 11 FLAG Guidance Exhibit 12 EPA Guidance for PM2.5 Modeling Exhibit 13 EPA NAAQS Table for criteria Air Pollutants Operating Manual for NOx Control Device
TEP PSD Air Quality Permit #1052 TEP PSD Technical Support Document (TSD) Pima County Responses to Public Comment Permit Issuance Decision Letter Compliance Assurance Monitoring Plan for Carbon Monoxide
TEP PSD Air Quality Permit #1052
TEP PSD Technical Support Document (TSD)
Pima County Responses to Public Comment
Permit Issuance Decision Letter
Compliance Assurance Monitoring Plan for Carbon Monoxide
Pencor Masada (May 2001) Citgo - Petition Order (May 2009) Cash Creek - Petition Order (June 2012) Pio Pico Energy - EAB Final Order (Aug 2013) Hu Honua - Petition Order (Feb 2014) Yuhuang - Order Denying Petition for Objection to Permit (April 2018) California Power Holdings - Permit to Operate
Pencor Masada (May 2001) Citgo - Petition Order (May 2009)
Cash Creek - Petition Order (June 2012)
Pio Pico Energy - EAB Final Order (Aug 2013)
Hu Honua - Petition Order (Feb 2014) Yuhuang - Order Denying Petition for Objection to Permit (April 2018)
California Power Holdings - Permit to Operate
The information below provides a chronological list of the documentation related to this complex process from the projects inception to its conclusion. PDEQ is utilizing this repository webpage to provide easy access to the documents for the public comment period and to facilitate an open dialogue and the sharing of information with all interested parties.
August 1, 2017 Permit Application Documentation
33 N. Stone Ave., Suite 700 Tucson, AZ 85701 Phone: (520) 724-7400 Fax: (520) 838-7432