  • *Update: Pavement Preservation Work on Swan Road and on Sunrise Drive

    Jul 20, 2018 | Read More News
    Share this page

    Pima County Department of Transportation along with their contractor, ViaSun Corporation, will be performing a micro seal treatment at the following locations:
    roads
    Tuesday, July 17 through Tuesday, July 24: The contractor will be performing a micro seal treatment on Swan Road from River Road to Sunrise Drive. Hours of operation will be from 6 a.m. to 5 p.m. Temporary striping to follow work

    Wednesday, July 25 through Wednesday, August 1: The contractor will be performing a micro seal treatment on Sunrise Drive from Craycroft Road to Hacienda del Sol Road. Hours of operation will be from 6 a.m. to 5 p.m. Temporary striping to follow work.

    Motorists can expect lane restrictions and reduced speed. Sheriff’s deputies, flaggers and a pilot car will be assisting through the work zone. Please approach the area with caution and obey all traffic control devices. Minor delays may occur during this work.

    In the event of mechanical failure or inclement weather, the construction schedule is subject to change.

    This project is part of the $6M Arterial and Collector Pavement Preservation Program for the fiscal year of July 1, 2017 through June 30, 2018. For a complete listing of the 2017/2018 Arterial and Collector Pavement Preservation Program, please visit:
    www.pima.gov/transportation .