DOT-57 S. Houghton, Camino Aurelia to I-10
Total Actual Cost: $1,250,180
Project Number: CTR.4SHRAI
Funding Sources: 1997 HURF Bonds, Other
Completion Date: December 2018
Managing Dept.: Transportation
Project Map: GIS Map
Houghton Road intersection improvements consisted of shoulder widening and left turn lanes at Brekke Road, Dawn Road, Andrada Road, and Camino del Emperador.