On Monday, March 2, Pima County Department of Transportation along with their contractor, Granite Construction, Inc., will be performing road repair work on Ina Road from Shama Wing to just east of the CDO Wash Bridge. The following is the work schedule:
Monday, March 2 through Friday, March 6: The contractor will be setting up message boards, traffic control devices and installation of loops. Hours of operation will be from 6 a.m. to 6 p.m.
Tuesday, March 10 through Friday, March 13: During the nighttime hours of 6 p.m. to 6 a.m., the contractor will be milling and repaving, temporary striping and raising utilities. Final striping will occur at the end of March.
Motorists can expect lane restrictions and reduced speed. Please approach the area with caution and obey all traffic control devices. Minor delays may occur during this work.
In the event of mechanical failure or inclement weather, the construction schedule is subject to change.
These projects are part of Pima County’s $36 million Road Repair Work Program for fiscal year July 1, 2019 through June 30, 2020. For a complete listing of the Road Repair Program, please visit www.pima.gov/roadrepairmap.