Total Project Cost: $557,291
Project Number: CFMCRBLDG
Funding Sources: 2004 General Obligation Bonds
Completion Date: January 2013
Managing Dept.: Pima County Facilities Management
Project Map: GIS Map
Phase IV, as with previous phases of the work at Canoa Ranch, was consistent with long term goals established by The Canoa Ranch Master Plan (2007). Phase IV was broken down into 5 tasks:
1. Ranch HQ-area Site Drainage
2. Power, Lighting, Water (Utilities)
3. Bldg 102 Restroom & associated Septic System
4. Bldg 106 Foundation repairs
5. Exterior repairs to Buildings (various)
All 5 major tasks outlined for this phase of work where able to be completed ensuring the long-term protection of the historic resources, as well as taking into account sensitive archaeological potential.