DOT-57 Tanque Verde Rd at Tanque Verde Loop Rd
Total Cost: $1,538,838
Project Number: CTR.4TVTVL
Funding Sources: STP, 1997 HURF Bonds, Arizona State Revenue
Completion Date: May 2020
Managing Dept.: Transportation
Project Map: GIS Map
The intersection of Tanque Verde Road and Tanque Verde Loop was converted from a three-legged stop-controlled intersection to a four-legged signalized intersection. An eastbound right-turn lane, median islands at the signal for the eastbound and westbound approaches, and exclusive left-turn lanes for the northbound and southbound approaches were constructed. In addition, shoulders along portions of Tanque Verde Loop Road south of the intersection were paved, sidewalks and ADA pedestrian access ramps along portions of both Tanque Verde Road and Tanque Verde Loop Road, street lighting at the traffic signal location, and signage on Tanque Verde for both east and west bound traffic were included in the intersection improvements.