  • DOT-59 Spdwy Blvd - Painted Hills Rd to Cmo de Oeste

    Total Actual Cost: $2,440,142
    Project Number:  CTR.4HSBSP
    Funding Sources: 1997 HURF Bonds
    Completion Date: May 2021 
    Managing Dept.: Transportation
    Project Map:  GIS Map

    1.7 miles of Speedway Boulevard was widened and improved between Painted Hills and Camino de Oeste. The existing roadway was widened to accommodate paved shoulders on each side of the roadway, with milling and replacement of the existing roadway pavement. A guardrail assessment was performed to evaluate the condition of the existing guardrail and provided a basis for the recommendation of any needed replacement.

    shoulder viewSpeedway Blvd improvements