  • Road Repair Work on both Wilmot Road and Kolb Road Starts January 31

    Jan 25, 2022 | Read More News
    Share this page

    Pavement PreservationBeginning Monday, January 31 through Friday, February 18, between 6 a.m. and 6 p.m., Pima County Department of Transportation and its contractor, Granite Construction, Inc., will be performing road repair work at the following locations:

    • Tuesday, February 1 and Wednesday, February 2: milling and repaving Wilmot Road from Hermans Road, south to the Tucson city limits.
    • Monday, February 14 and Tuesday, February 15: milling and repaving Kolb Road from south of the I-10 to Voyager Road.

     

    The work will start with setting traffic control, lowering utilities, followed by milling and repaving, temporary striping, and cleanup. Thermo striping is scheduled for February 18.

    Flaggers will be on site to direct, monitor and control traffic movements through the construction zone. Please approach the area with caution and obey all traffic control devices. Minor delays may occur during this work.

    In the event of mechanical failure or inclement weather, the construction schedule is subject to change.

    In Fiscal Year 2021/2022, the Pima County Board of Supervisors and Transportation Department allocated $85 million in road repair and preservation funding for the Road Repair and Preservation Program. To learn about the Department of Transportation’s Pavement Preservation Program and the projects that are currently scheduled, please visit www.pima.gov/RoadRepairMap.