DOT-41 & DOT-57 Pavement Preservation Projects FY2014
Total Actual Cost: $ 6,366,668
Project Number: CTR4PPP14
Funding Sources: 1997 HURF Bonds, County HURF, Other
Completion Date: Nov 2014
Managing Dept.: Transportation Dept.
Project Map: GIS Map
A total of 29 miles of roadway were preserved with this project. A variety of pavement preservation methods were used depending on the condition of the existing pavement including: chip seal, mill and fill, and structural overlay. It included $1.7M of work in District 2 funded with DOT-41 HURF Bonds.