DOT-41 Cherry Avenue Curbs & Sidewalks
Total Actual Cost: $ 170,000
Project Number: CTR4CEDCA
Funding Sources: 1997 HURF Bonds
Completion Date: January 2012
Managing Dept.: Transportation
Project Map: GIS Map
This project provided curbing, sidewalks and paving at a high-capacity intersection and heavily trafficked entry point into the Miles Neighborhood. The improvements serve a high number of pedestrians and provide better
access to the various businesses and schools in the vicinity of Cherry Avenue and Broadway Boulevard. The project was built in cooperation with the City of Tucson.