Total Actual Cost: $45,000
Project Number: CTR.4HAWKS
Funding Sources: 1997 HURF Bonds
Completion Date: March 2018
Managing Dept.: Transportation
Project Map: Multiple locations county-wide
The HAWK Installation Project was created to have a consultant, PSOMAS, identify and prioritize potential crosswalk locations for Hybrid Pedestrian Beacons (HAWKs). The design and installation of HAWKs would be completed by Pima County DOT Traffic Engineering Division.
Following the Department reorganization at the beginning of Fiscal Year 2019, it was decided by DOT management to have the newly created Analytics and Planning Division do the project identification.
The consultant was directed to complete Assignment 1 of the current scope of the top ten potential sites.