• Increase font size
  • Decrease font size
  • Print
  • RSS
  • Status of Bond Projects

    Pima County’s project delivery process for completing these projects has become a model adopted by other governmental agencies in Pima County, Phoenix and Texas.

    Completed Bond Programs

    1997 Sewer Revenue
    1997 General Obligation
    2004 Sewer Revenue
    2004 General Obligation
    2006 General Obligation (Behavioral Health Facilities)

    Substantially Completed Bond Programs

    2014 General Obligation (Pima Animal Care Center)

    Active Bond Programs

    1997 HURF (Transportation)

    2014 General Obligation Bond Program, Pima Animal Care Center - Substantially Complete

    For the latest on the constuction, see our Construction Progress page.







    Construction of the new Pima Animal Care Center (PACC) was completed in December 2017 and renovation of the old facility was completed in July 2018. A fence with controlled access vehicular gates was completed in December 2019, to secure the front of the facility when not open to the public, and to reduce the staffing demand for drop-offs prior to opening and after closing. PACC receives bulk food donations several times a year but did not have a dedicated facility to store the 100 or more pallets of food that are donated. A building located at the former Pima County Wastewater Reclamation site was identified as an option, but required improvements. The improvements were completed in the Spring of 2020 and included a HVAC system, upgraded power for the new HVAC system, insulating the building and a forklift for unloading/loading the pallets. Approximately $485,000 in bond proceeds remain. Additional improvements to the Silverbell Road Facility are being evaluated, as well as improving off-site services. 

    1997 General Obligation Bond Program - Substantially Complete

    In May 1997, Pima County voters approved $257 million in general obligation bonds for a variety of capital improvement projects throughout Pima County, including within cities and towns.

    Completed bond projects include:

    • A new adult detention facility, a new juvenile detention facility and court complex, and 11 Superior Court courtrooms
    • 2 new libraries, 5 new pools, 8 new community centers, 11 new or expanded regional parks, 16 neighborhood parks, 9 miles of river parks, expansion of Tucson Mountain Park and acquisition of Canoa Ranch
    • A levee along seven miles of the northern bank of the Santa Cruz River protecting a major portion of Marana
    • Expansion of the Sahuarita Landfill, closure of the Tangerine Landfill, and many other facility improvements.

    2004 General Obligation Bond Program - Substantially Complete

    In May 2004, Pima County voters approved $582.2 million in General Obligation bonds for a variety of capital improvement projects and land acquisitions throughout Pima County, including within cities, towns and tribal areas.                                                                                                                                                                                                  

    Completed bond projects include:

    • A new emergency communications system used by 55 emergency service providers
    • A new public service center, public health center and interagency victim advocacy center
    • New and improved libraries, community centers, museums, parks and recreational facilities
    • Hundreds of new affordable housing units
    • Many miles of new flood control improvements
    • Hundreds of acres purchased to prevent urban encroachment on Davis-Monthan Air Force Base
    • Thousands of acres purchased to serve as mitigation for future development while expanding             nature-based recreational opportunities
    • Rehabilitation of historic buildings and purchase of priority archaeological sites

    1997 HURF Revenue Bond Program – Active

    During the first half of Fiscal Year 2020 (July 1 through December 31, 2019), the transportation bond project DOT-57 Ina Road - Shannon Road to La Cholla Boulevard Sidewalks and the Speed Management Study were completed.

    Remaining Pima County Managed Projects

    1. DOT-32, Kolb Road - Sabino Road to Sunrise Drive: Under development. Construction to start in fall 2020.

    2. DOT-59, Road Repair and Pavement Preservation: Construction was completed at the end of June 2020,
        with the exception of Speedway Blvd. – Painted Hills Road to Camino de Oeste, with is currently under
        construction.

    3. DOT-57, Safety Improvements: The following projects are under development or under construction.

        • Speedway Blvd - Painted Hills Rd to Camino de Oeste: Under construction.
        • King Canyon Trailhead Parking: Under development. Construction to start in late Fall 2020.
        • Bopp Rd - Sarasota Blvd. at Kinney Rd Improvements: Under construction.
        • SMART Transportation Data Network: Under development.
        • White Elementary School - Pistor Middle School: Under construction. Completion is anticipated by end
           of August 2020.
        • Skyline Drive at Sunrise Drive Intersection Improvements: Under development. Construction to start in                   Summer 2020.
        • Sign Panel Replacement: Under development. Procurement of signs started in Spring 2020.

    Remaining City of Tucson Managed Projects

    1. DOT-29, Houghton Road - Golf Links Road to Interstate 10: Remaining County bond funding will be                      contributed to the Valencia Road to Mary Ann Cleveland Way phase of the project that is scheduled to
        start construction this Fiscal Year. The County's bond funds are scheduled to be spend this Fiscal Year
        and next (FY 2020/21 and FY 2021/22).

    2. DOT-56, Broadway Boulevard - Euclid Avenue to Country Club Road: Construction has begun and is
         scheduled to last for two years. $15.7 million of the County's bond funds have been spent on this
         project, and it is anticipated that the remaining $9.3 million in County bond funds will be spent this Fiscal
         Year.

    3. DOT-58, 22nd Street - Interstate 10 to Tucson Boulevard:  This project has multiple phases. Construction
         of the Kino to Tucson Boulevard phase includes County bond funding. Design is complete and
         construction is pending additional non-County funding.

    Any HURF bond authorization remaining after completion of these projects can remain unsold, or reallocated to other projects. Reallocation of bond authorization to other projects would require a bond ordinance amendment following the public notification and hearing process stated in County Code.

    Over 700 Projects Completed since 1997

    The following links feature summaries and maps of completed projects.







    Pima County Bonds Interactive Map







    Interactive Bond Project Maps

    Completed Bond Projects From 1997, 2004 and 2006 Elections Interactive Map







    Interactive maps are supported on Internet Explorer 9 and above (download), Chrome, Firefox, Safari and the most recent tablet and smartphone devices.
    Follow UsShare or bookmark this page

    Pima County Bonds

    (520) 724-8450


    Department Home
    Bond News
    Department Directory
    Feedback
    Boards, Commissions and Committees